Production information report for design and construction
The production information report is a work stage report produced by the consultant team for the client at the end of the production information stage (see free work plans on the Designing Buildings Wiki home page).
It is the last opportunity for the client to consider issues to do with the design of the development and the form of contract before the tender process begins. It may also be the first time that the client has seen drawings describing key components (such as door handles), assemblies and specialist items. As a result, the client may wish to issue the production information report (or parts of it) for consideration to key users (or user panels) and perhaps to their lawyer or other independent client advisers. Once the main contractor has been appointed, subsequent changes can become very expensive.
The production information report may include:
- The approximate quantities cost plan and cash flow projection.
- Packaging strategy (and costs associated with individual packages).
- An assessment of cost uncertainty and the reasons for this.
- Identification of provisional sums.
- A schedule of outstanding information (including any client contributions that will be required for the contract documents).
- A schedule of outstanding consents (such as statutory approvals or planning conditions).
- A description of proposed preliminaries and other items to bring to the client's attention.
- Proposed warranties and bonds.
- The proposed form of contract, contract conditions and any proposed changes to the contract.
- Proposed treatment of liquidated damages.
- A schedule of exclusions from the contract.
- Any insurance issues.
- Drawings and specifications describing key components, assemblies and specialist items.
- A list of any remaining components, assemblies, specialist items, samples or materials still requiring approval by client.
- An assessment of the possible use of preliminary contracts.
- An assessment of the possibility of ordering long-lead items early.
- The proposed date of possession.
- Tender procedures and the tender period.
- An assessment of the need to appoint site inspectors.
- An assessment of the need to appoint party wall surveyor(s).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.